Scrum and Kanban teams in an ART in EAP

concept australia Updated Oct 2, 2026 2 min read scrum-and-kanban-teams-in-eap.md
Raw file servicenow.com

Run Scrum and Kanban teams side by side in one Agile Release Train (ART) in Enterprise Agile Planning by setting the planning methodology for each Agile Team.

An ART can include teams that work in different ways. Each Agile Team follows one of two planning methodologies, Scrum or Kanban.

Scrum and Kanban teams comparison

  • Scrum

    The team plans work in Sprints. Sprints follow the planning calendar of the team or its ART.

  • Kanban

    The team works from a continuous backlog. Kanban teams have no Sprints and don't use the shared calendar of their ART.

Kanban team differences

Because a Kanban team doesn't use Sprints, the following differences apply:

  • Backlog

    The Create Sprint button isn't available on the team Backlog.

  • Sprint creation

    When you create a Planning Interval for the ART, or add child Sprints, Sprints are created for Scrum teams only. Kanban teams are skipped.

  • Story forms

    The Iteration field is hidden on the forms of stories assigned to a Kanban team.

  • Sprint states

    You can't change the state of a Sprint that belongs to a Kanban team, except to complete or cancel it.

  • Home tab

    The Home tab of a Kanban team shows the Kanban Team dashboard instead of the Scrum dashboards. For more information, see Kanban Team dashboard in EAP.

  • Planning board

    The Planning board of an ART doesn't display its Kanban teams, because they don't use iterations. A message indicates that some teams might not be displayed. For more information, see Perform PI planning in EAP.

Team planning methodology

The Planning methodology field appears above the Calendar field on the Agile Team form. New teams default to Scrum. ARTs, Solution Trains, and Portfolios don't have this field.

When you add Agile Teams to an ART, you choose the planning methodology first. The choice applies to all teams that you add in that batch. For more information, see Define agile structure in EAP.

Methodology after an upgrade

When you upgrade, existing Agile Teams that have a calendar of their own or a calendar from their configuration are set to Scrum. All other existing Agile Teams are set to Kanban.

Team methodology changes

To move a team from Scrum to Kanban, see Switch an Agile Team to Kanban in EAP. Switching a Scrum team to Kanban cancels the current and future Sprints of the team.