Review external dependencies between projects
Review the external dependencies between projects in a portfolio to track projects that are dependant on each other more closely.
Before you begin
Role required: it_portfolio_manager
Open demands and projects in the timeline view of the Portfolio Planning Workbench.
About this task
As a portfolio manager, you may want to know the projects which are dependent on each other so that these projects can be tracked more closely.
For example, project B is dependent on project A (external soft dependency) and you want to make sure that project A is executed on time so that the schedule of project B is not affected. The Dependencies column shows that there is an outgoing external dependency from project A and an incoming external dependency to project B. You can the use the incoming dependency to determine whether a delay in project A will affect project B.
Procedure
-
Click the show or hide columns in gantt icon ([Omitted image "show_hide_columns.png"] Alt text: show or hide columns in gantt) in the timeline view and add the Dependencies column if it is not visible.
The number of incoming and outgoing external dependencies are displayed, if any.
-
Click the external dependency in Dependencies column for the project.
-
In the Dependencies pop-up dialog, click a tab to review the dependency:
-
Inbound tab
Tasks that have an incoming dependency from a project are listed.
-
Outbound tab
Tasks with an outgoing dependency to the project are listed.
[Omitted image "ReviewExternalDependencies.png"] Alt text: Dependencies example
-
-
Click the project number in a tab to open and review the linked project in the planning console view.
Parent Topic:Create planning scenarios
---
title: Review external dependencies between projects
description: Review the external dependencies between projects in a portfolio to track projects that are dependant on each other more closely.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/portfolio-management/sp-review-ext-dependencies-between-prj.html
release: australia
product: Portfolio Management
classification: portfolio-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 1
breadcrumb: [Create planning scenarios, Scenario Planning for PPM, Portfolio Management, Project Portfolio Management, Strategic Portfolio Management]
---
# Review external dependencies between projects
Review the external dependencies between projects in a portfolio to track projects that are dependant on each other more closely.
## Before you begin
Role required: it\_portfolio\_manager
Open demands and projects in the timeline view of the Portfolio Planning Workbench.
## About this task
As a portfolio manager, you may want to know the projects which are dependent on each other so that these projects can be tracked more closely.
For example, project B is dependent on project A \(external soft dependency\) and you want to make sure that project A is executed on time so that the schedule of project B is not affected. The **Dependencies** column shows that there is an outgoing external dependency from project A and an incoming external dependency to project B. You can the use the incoming dependency to determine whether a delay in project A will affect project B.
## Procedure
1. Click the show or hide columns in gantt icon \(\[Omitted image "show\_hide\_columns.png"\] Alt text: show or hide columns in gantt\) in the timeline view and add the **Dependencies** column if it is not visible.
The number of incoming and outgoing external dependencies are displayed, if any.
2. Click the external dependency in **Dependencies** column for the project.
3. In the **Dependencies** pop-up dialog, click a tab to review the dependency:
- **Inbound tab**
Tasks that have an incoming dependency from a project are listed.
- **Outbound tab**
Tasks with an outgoing dependency to the project are listed.
\[Omitted image "ReviewExternalDependencies.png"\] Alt text: Dependencies example
4. Click the project number in a tab to open and review the linked project in the planning console view.
**Parent Topic:**[Create planning scenarios](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/portfolio-management/create-scenarios.md)
| title | Review external dependencies between projects |
| description | Review the external dependencies between projects in a portfolio to track projects that are dependant on each other more closely. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/australia/it-business-management/portfolio-management/sp-review-ext-dependencies-between-prj.html |
| release | australia |
| product | Portfolio Management |
| classification | portfolio-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 1 |
| breadcrumb | Create planning scenariosScenario Planning for PPMPortfolio ManagementProject Portfolio ManagementStrategic Portfolio Management |