Legacy- Track the portfolio

task australia Updated Sep 10, 2026 4 min read t_ReviewFinancialPlanning.md
Raw file servicenow.com

After you complete financial planning, you can start tracking the progress of the portfolio. The portfolio tracking view displays only the selected demands and projects in the portfolio.

Before you begin

Role required: it_portfolio_manager

About this task

Note: The content in this topic is applicable for customers upgrading from a previous release to Brazil. If you are a new customer, see Scenario Planning for PPM.

Once the financial planning is complete, the Track Portfolio action in the portfolio workbench is enabled to start tracking the progress of the portfolio.

Watch this three-minute video to learn more about tracking your portfolio.

Procedure

  1. Navigate to portfolio workbench, and open the portfolio that you want to track.

  2. In the Fiscal Year choice list, select the fiscal year and click Track Portfolio.

  3. In the timeline view, right-click a project or a demand and select:

    • Edit to edit the project or the demand.
    • Planning Console to open the project planning console. The option is available only for projects.
    • Status Report to open the most recent project status report. The option is available only for projects.
  4. In the timeline view, review the external dependencies between projects in a portfolio.

  5. On the Project KPI tab, view the most recent status such as overall health, schedule, cost, resources, and scope of all selected projects in the portfolio.

  6. Review these charts:

    • Cost (Planned vs. Actual) to track the actual costs from all selected projects in the portfolio compared to the planned cost.
    • Resource (Allocated vs. Actual) to track the actual resource time spent on all project tasks versus the resource hours allocated to execute the selected projects and demands in the portfolio.
  7. To see the risks, issues, and the project change requests across all selected projects in the portfolio, use the Risks, Issues, and Changes tabs.

What to do next

Legacy- Forecast the budget for portfolio.

  • Legacy- Tracking view in portfolio workbench
    Once the financial planning is complete, the Track Portfolio option in portfolio workbench is enabled. You can track the progress of demands and projects, and monitor the status of cost, resource, schedule, and scope for the selected fiscal period for the portfolio.

Parent Topic:Legacy portfolio workbench

Related topics

Access the legacy Portfolio workbench

Legacy- Plan the portfolio

Legacy- Forecast the budget for portfolio

Actual project costs