Generate labor costs for a demand
Generate labor costs to view the expenses of resources using resource assignments and cost plans for a demand.
Before you begin
Role required: it_demand_manager
About this task
When the effort distribution for a resource assignment changes without changing the total planned effort, labor costs are recalculated automatically. The recalculated costs align with the updated effort distribution. For example, consider a resource assignment of 100 hours: 60 hours in January and 40 hours in February. If you swap the efforts to 40 hours in January and 60 hours in February, labor costs are recalculated automatically. January then reflects the cost of 40 hours and February reflects the cost of 60 hours.
Procedure
-
Navigate to Workspaces > Portfolio Planning Workspace.
-
Select the Demands icon [Omitted image "demands-icon.png"].
-
Open a demand from the List page.
-
Select Financials from the navigation menu.
-
Select Generate labor costs.
-
Select Generate in the Generate labor costs confirmation window.
Tip: Configure a scheduled job to generate labor costs at the required cadence. For more information, see Activate a scheduled job to generate labor costs.
---
title: Generate labor costs for a demand
description: Generate labor costs to view the expenses of resources using resource assignments and cost plans for a demand.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/portfolio-planning/generate-labor-costs-ppw.html
release: australia
product: Portfolio Planning
classification: portfolio-planning
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 1
breadcrumb: [Manage financials for demands, Use, Next Experience for Demand Management in Portfolio Planning, Portfolio Planning, Strategic Portfolio Management]
---
# Generate labor costs for a demand
Generate labor costs to view the expenses of resources using resource assignments and cost plans for a demand.
## Before you begin
Role required: it\_demand\_manager
## About this task
When the effort distribution for a resource assignment changes without changing the total planned effort, labor costs are recalculated automatically. The recalculated costs align with the updated effort distribution. For example, consider a resource assignment of 100 hours: 60 hours in January and 40 hours in February. If you swap the efforts to 40 hours in January and 60 hours in February, labor costs are recalculated automatically. January then reflects the cost of 40 hours and February reflects the cost of 60 hours.
## Procedure
1. Navigate to **Workspaces** > **Portfolio Planning Workspace**.
2. Select the Demands icon \[Omitted image "demands-icon.png"\].
3. Open a demand from the **List** page.
4. Select **Financials** from the navigation menu.
5. Select **Generate labor costs**.
6. Select **Generate** in the Generate labor costs confirmation window.
**Tip:** Configure a scheduled job to generate labor costs at the required cadence. For more information, see [Activate a scheduled job to generate labor costs](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/gen-labor-costs-scheduled-job-ppm.md).
| title | Generate labor costs for a demand |
| description | Generate labor costs to view the expenses of resources using resource assignments and cost plans for a demand. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/australia/it-business-management/portfolio-planning/generate-labor-costs-ppw.html |
| release | australia |
| product | Portfolio Planning |
| classification | portfolio-planning |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 1 |
| breadcrumb | Manage financials for demandsUseNext Experience for Demand Management in Portfolio PlanningPortfolio PlanningStrategic Portfolio Management |