As a project manager, you might create a request change as the outcome of the action taken to resolve an issue or mitigate a risk. The request change might result in changing the project's scope, resource requirement, cost, or schedule to minimize the impact of a risk or issue.

Before you begin

Role required: it_project_manager

Procedure

  1. Navigate to Project > Projects > All.

  2. Select the project to which you want to add a request change.

  3. In the Request Changes related list and select New.

  4. On the form, fill in the fields.

    For more information, see RIDAC form fields.

  5. Select Submit.

What to do next