Planning console tasks

reference australia Updated Sep 10, 2026 13 min read r_PlanningConsoleTasks.md
Raw file servicenow.com

You can perform several tasks on the planning console that you can perform on lists and forms, such as creating project tasks and copying projects. You can also perform several tasks unique to the console.

Task Steps
Display a project in the planning console Select the project from the list in the project workspace banner.

Task

Steps

Create a project task

Select the add task below icon on the row to create a new task.

To control the insertion point, select an existing task first. Then select the add task above icon or the add task below icon.

Move a task up or down in the hierarchy

Select an existing task, and then select the move up or move down icons.

Indent or unindent a task in the hierarchy

Select an existing task, and then select the unindent or indent icons.

Edit a task record

Right-click a task and select Edit. The Project Task form appears in the overlay. You can also edit a field directly in one of the columns in the planning console. You can also edit project tasks that represent phases in the project workbench.

Edit the State field

Double-click the value in the State column to select a new state. The value of the State field also changes automatically when % complete is changed for a task.

View and modify task status

View the status of the project task based on the difference of the planned end date of the task from the current date. The status of the task updates automatically from Green to Yellow to Red as the planned end date approaches.You can manually update the task status by double-clicking the Status column and selecting a different task status. For more information, see Status field description in the Create a project task from a project topic.

Add an agile phase or a test phase

Right-click a project and select Add Agile Phase or Add Test Phase. The agile phase icon or test phase icons appear next to the task in the Name column. See phase icons. Note:

  • The Add Agile Phase option is available only for Agile and Hybrid projects. You must also have the Agile Development 2.0 plugin installed.
  • You can add multiple agile phases and multiple test phases to a project.
  • You can add only one test phase for a test plan in a project. You must have the Test Management plugin installed to view the Add Test Phase option.
  • An agile phase cannot overlap another agile phase for an assignment group in a project.
  • While creating a story, if a project has only one phase, then the story is tagged to the phase.

Open a test plan or story

Right-click a task (a task that represents a phase in the workbench) and then select Manage Test Plan. Select View Stories to view the stories list. If you have the scrum_product_owner role, select View Stories to navigate to the Backlog tab of the Agile Board.Note: The View Stories option is available only for Agile and Hybrid projects. You must also have the Agile Development 2.0 plugin installed.

Cancel a resource plan for a Closed project

Right-click the project and select Cancel Resource Plans. All past and future allocations for the selected resource plan are canceled.The option is available only for a project in any of the Closed states.

Complete a resource plan for a Closed project

Right-click the project and select Complete Resource Plans. All the requested and resource allocations for the resource plan post the completion date are deleted.The option to complete resource plans is available only for a project in any of the Closed states.

Add an external dependency between tasks of different projects

Right-click a task and select Add External Dependency. Select the project and task to which the dependency is added.

View the project name of an external dependency

Point to the link icon beside the external dependency task to display a tooltip which shows the name of the project to which the external dependency is added.

Change the time constraint for a task

Double-click a task under the Constraint type column and select an option: Start ASAP, Start on specific date, Start no earlier than, or Start no later than.- You can change the Constraint type for Automatic projects only.

  • When you change the time constraint for a task from Start on specific date to Start ASAP or vice versa, the planned start date and planned end date of the task are recalculated accordingly.
  • The Constraint date column displays the start date for all the constraint types other than Start ASAP tasks. This column is not available by default, you must add this column to the Planning Console from the Configuration menu.
  • The option is not available for a parent task. If a task has child tasks, the option is available only for the child tasks.
  • You cannot create a parent task with Start no later than or Start on specific date time constraint. When a new child task is added to a task with these time constraints, the time constraint for the parent task is converted to Start ASAP.
  • You cannot change constraint type for projects with Calculation type set as Manual.

Allow task dates outside schedule

Right-click a project task and select Allow outside schedule. The selected task is allowed to start and end on a non-schedule day (outside the regular project schedule) such as on a weekend. The off schedule task icon appears next to the task in the Short description column.If you use the project schedule Monday to Friday, 8:00 to 17:00 and a project task of duration 2 days starting Saturday. Then an off-schedule task is allowed to be scheduled on Saturday and end on Sunday. Similarly, if a task of duration 3 days starts on Friday, then an off-schedule will end on Sunday as opposed to ending on Tuesday.

  • The option is not available for a parent task. When a task is made off-schedule, its parent also becomes off-schedule. The project also operates as out of schedule if any of the children is set to out of schedule.
  • Once a task is allowed outside the schedule, the Follow schedule option is available for the task. Right-click the task and select Follow schedule to follow the schedule for the task.

Note:

  • There is no difference between an off-schedule and an on-schedule task if there is no schedule defined at the project level.
  • 1 day is 8 hours for a task in a regular schedule and 24 hours for a task outside the schedule.

Convert a task to milestone

Right-click a task and select Convert to milestone. - You can convert a task to a milestone only until it is not in Work in Progress state. Once work in progress, the option appears as greyed out for the task.

  • The option is not available for a parent task. If a task has child tasks, the option is available only for the child tasks.

Show or hide external dependencies

Select the more options icon, and then select the Hide External Dependencies switch. When this option is enabled, the external dependencies are not displayed when you add an external dependency between two projects. However, the Dependency column in the WBS section of the successor project still shows the value of external dependency.

Show external dependency notifications

Select the notification bell icon to display the notifications raised in the successor project. The notifications are triggered as a result of changes made in the predecessor project.- For a soft dependency, select Accept or Reject to accept or reject the changes in the notification.

  • For a hard dependency, view the displayed notification to review the changes in the notification.

Save changes to the server

Select the save icon to commit changes made in the planning console. The option is available only when Client Side Planning Console is enabled.

Expand or contract column width

Select the side of the column and drag it right or left.

Show or hide columns in the planning console

Select the show or hide columns in gantt icon, and then select or clear the check boxes for the columns available. Admin can customize which columns appear in this list. The selection is saved in the user preference. The next time you open the planning console, the same columns you selected will appear.

Select WBS levels to show

Select the show or hide columns in gantt icon, and then select the level from the WBS Depth list.

Expand or collapse sublevels for any level

Select the arrow to expand or collapse any task that has one or more subtasks.

Task

How to perform the task

View a summary of a task

Point to a task.

Change the planned start or end dates of a task

Select the task, and then drag the left or right edge of the task bar.

Move a task to a new date

Select the task, and then drag the whole task bar to a new location.

Create a dependency between tasks

Find the successor task in the relationship and double-click the value in the Predecessor column and enter a value that specifies the relationship. See Predecessor dependencies in the planning console for examples.Alternatively, you can create a relationship between two tasks by connecting the ends of the corresponding task bars in the timeline view.

Select a baseline

Select the more options icon, and then select a baseline from the baselines list.

Create a baseline

Select the more options icon, and then select Create new baseline. See Create baseline of a project for more information.

Compare schedule baselines

Select the more options icon, and then select a schedule baseline from the baselines list. Select the show or hide columns in gantt icon, and then select the following columns to compare schedule baselines:- Baseline start date

  • Baseline end date
  • Baseline variance

Display the critical path

Select the critical path icon. For more information on the critical path, see Gantt chart.

Show date change

Select the more options icon, and then select the Show Date Change switch. When this option is enabled, the start and end dates of the task are displayed when you drag the task bar.

Show duration change

Select the more options icon (), and then select the Show Duration Change switch. When this option is enabled, the duration of the task is displayed when you drag either end of the task bar.

Show weekends on the calendar

Select the more options icon, and then select the Show Weekends switch. The weekends appear as light-blue vertical bars in the Gantt chart.

Zoom the calendar in or out

On the top of the calendar, select one of the time periods, such as the month or day. Then select a Zoom Level from the calendar.When the zoom level is set to Auto Fit, the Gantt view fits on one page. The entire project timeline is visible without scrolling.

Open the tutorial

Select the more options icon (), and then select Walkthrough.

Open list of keyboard shortcuts

Select the more options icon, and then select Keyboard Shortcuts.

Task

How to perform the task

Open the project workbench

Select the Planning Console selection arrow on the banner and select Project Workbench. For more information, see Using Project workbench - Legacy.

Open live feed

Select the more options icon, and then select Show live feed.

Export project data in MPP, CSV, or XML format

Select the more options icon, and then select Export Planning Console. For more information, see Export project data.

Print the gantt timeline

Select the more options icon, and then select Print.Note:

  • Printing on a smaller paper size might result in the gantt chart image being cut off. You may either zoom out using the gantt chart calendar, or increase paper size to print the gantt timeline for projects and tasks.
  • If the colored bars in gantt chart area are not visible in Print preview, then select the option for background graphics in the Print dialog.