RIDAC form fields

reference australia Updated Sep 10, 2026 7 min read ridac-forms.md
Raw file servicenow.com

Learn about the fields of the RIDAC form.

Field

Description

Number

System-generated ID number with a configurable prefix.

State

Current state of the risk. All new risks are created in the Pending state.The available states are: Pending, Open, Work in Progress, Closed Complete, Closed Incomplete, and Closed Skipped.

Risk status

Status of the risk. It provides information on current status of the risk, whether it is achieved or mitigated or accepted. The available options are: Pending, Achieved, Not Achieved, Avoid, Mitigate, Transfer, and Accept.

Probability

The likelihood that the event described in the risk will occur. The available options are: Absolute, High, Moderate, and Low

Impact

Impact of the risk event on the outcome of the project.

Estimated cost

Estimated cost the risk event generates.

Risk rank

A value and color assigned to the risk. This value is calculated using risk probability and impact. You can configure the color and value using Risk Value Lookup. For more information, see Configure custom Risk rank and Risk value for a project.

Risk owner

Primary resource who is responsible for monitoring and managing the risk.

Assigned to

Primary resource assigned to work on the risk.

Risk value

A value calculated from Risk Value Lookup. For more information, see Configure custom Risk rank and Risk value for a project.

Due date

Requested date for the assigned resource to resolve the risk or the date on which the risk must be closed or addressed if not assigned to any resource.

Show on project status report

Option to specify whether the risk information should be included in the project status report.

Task

Project to which this risk belongs.

Short description

Brief description of the event and its potential impact on the success of the project. If the risk is created from the risk library, then this field displays the Risk Statement name.

Description

Details of the event and its potential impact. If the risk is created from the risk library, then this field displays the Risk Statement short description.

Actual cost

Cost generated by the risk event. This information gets added when and if the event occurs.

Mitigation plan

Brief description of efforts taken to mitigate the risk.

|Field|Description| |-----|-----------| |Inherent risk|This field gets auto-populated with the risk scores when the risk assessor assesses the inherent risk.| |Elevated to enterprise risk|This option gets selected automatically when the risk is elevated to enterprise risk by the project manager.| |Residual risk|This field gets auto-populated with the risk scores when the risk assessor assess the residual risk.| |Enterprise inherent risk|This field gets auto-populated with the risk scores when the risk assessor assesses the enterprise inherent risk.| |Enterprise residual risk|This field gets auto-populated with the risk scores when the risk assessor assesses the enterprise residual risk.|

Field

Description

Number

System-generated ID number with a configurable prefix.

State

Current state of the issue. All new issue records are created in the Open state.The available states are: Pending, Open, Work in Progress, Closed Complete, Closed Incomplete, and Closed Skipped

Priority

Urgency of resolving or managing the issue based on possible impact.

Estimated cost

Estimated cost the issue generates.

Impact

Impact on the outcome of the project if the issue remains unresolved.

Due date

Requested date for the assigned resource to resolve the issue or the date on which the issue must be closed or addressed if not assigned to any resource.

Assigned to

Primary resource assigned to work on the issue resolution.

Parent

Project to which this issue belongs.

Show on project status report

Option to specify whether the issue information should be included in the project status report.

Short description

Brief description of the issue and its potential impact on the success of the project.

As you start typing the title for your issue, related issues that potentially match your issue are displayed.

Select the suggestion icon ([Omitted image "suggestions-icon.png"] Alt text: Suggestion icon) to select from the list of predefined issue descriptions.

Description

Details of the issue and its potential impact.

Work notes

Information to record and track the work accomplished for resolving the issue.

Field

Description

Number

System-generated ID number with a configurable prefix.

State

Current state of the decision. All new decision records are created with Open state.The available states are: Pending, Open, Work in Progress, Closed Complete, Closed Incomplete, and Closed Skipped

Priority

Urgency of approving or implementing the decision based on possible impact.

Decision status

Status of the decision. The available options are: Pending, Approved, and Rejected.

Impact

Impact on the outcome of the project if you do not implement the decision.

Approval required

Option for determining whether approval of the decision is required.

Estimated Cost

Estimated cost of implementing the decision.

Due date

Requested date on which the decision must be approved or implemented.

Assigned to

Primary resource assigned to work on the decision. The default value is the name of the user creating the decision record.

Parent

Project number to which this decision belongs.

Show on project status report

Option to specify whether the decision information should be included in the project status report.

Short description

Brief description of the decision such as what the decision is about, who made it, what it affects, and the decision outcome.As you start typing the title for your decision, related decisions that potentially match your decision are displayed.

Select the Suggestion icon ([Omitted image "suggestions-icon.png"] Alt text: Suggestion icon) to select a description from the list of predefined decision descriptions.

Description

Details of the decision and its potential impact.

Work notes

Information to record and track the status of decision implementation or approvals.

Field

Description

Number

System-generated number with a configurable prefix.

State

Current state of the action. All new action records are created with the state set to Open.The available states are: Pending, Open, Work in Progress, Closed Complete, Closed Incomplete, and Closed Skipped

Priority

Urgency for implementing or approving the action based on impact.

Estimated Cost

Estimated cost the action generates.

Impact

The impact on the outcome of the project if you do not implement the action.

Approval

Status of approval from the stakeholders for the action. A user with approval administrator role can only change the status of approval.

Assigned to

Primary resource assigned to implement the action.

Due date

Requested date on which the action must be approved or implemented.

Parent

The project to which this action belongs.

Show on project status report

Option to specify whether the action information should be included in the project status report.

Short description

Brief description of the action such as what the action entails, how to implement the action, who it affects, and the action outcome.As you start typing the title for your action, the related actions that potentially match your action title appear.

Select the Suggestion icon ([Omitted image "suggestions-icon.png"] Alt text: suggestion icon) to select a description from the list of predefined actions.

Description

Details of the action and its potential impact.

Work notes

Information about the action. Add work notes to communicate about the status of action approval, rejection, or implementation with other users.

Field

Description

Number

System-generated ID number with a configurable prefix.

State

Current state of the request change. All new request change records are created in the Open state.The available states are: Pending, Open, Work in Progress, Closed Complete, Closed Incomplete, and Closed Skipped

Priority

Urgency for approving the requested changes based on impact.

Estimated Cost

Estimated cost the requested changes generate.

Impact

Impact on the outcome of the project if you do not approve the requested changes.

Approval

Status of approval from the stakeholders for the requested changes.

Assigned to

Primary resource assigned to work on the request change.

Due date

Requested date to complete the request change.

Category

Entity for which you are creating the request change. The options are: Resource, Scope, Cost, and Schedule.

Parent

Project number to which this request change belongs.

Show on project status report

Option to specify whether the request change information should be included in the project status report.

Title

Title for the change request.

Description

Details of the request change and its potential impact.

Business Justification

Reason for requesting the proposed change in the project and its impact on the business.

Work notes

Additional information to indicate progress on the project request change.

**Parent Topic:**[Form field information for Project Management](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/form-field-information-for-project-management.md)
Search documentation
Search document titles and file paths on the australia branch