Create a parent-child relationship on the planning console
The WBS section of the planning console allows you to create parent-child relationships for new tasks or move around existing tasks in a new parent-child relationship. The position of a task in the hierarchy and the level of indentation determine the parent-child relationship it has with the tasks above or below it.
Before you begin
Role required: it_project_manager
About this task
In this example, the System Readiness Assessment task is a child of the Planning task because it is one level below the Planning task and is indented.
[Omitted image "example_parent-child-task.png"] Alt text: Parent-child task example
Procedure
-
Select a task in the WBS section of the planning console to highlight it.
-
Select a combination of any of the following icons to create the task and move it or move the other tasks to create the required hierarchy:
Icon Action Add task above icon ([Omitted image "add_task_above.png"] Alt text: Add task icon) Create a task above the highlighted task. Add task below icon ([Omitted image "add_task_below.png"] Alt text: Add task icon) Create a task below the highlighted task. Indent icon ([Omitted image "demote_icon.png"] Alt text: Indent icon) Makes the highlighted task a child of the task above it.
Parent Topic:Using Planning console - Legacy
Related topics
Open the project planning console
Predecessor dependencies in the planning console
Custom columns in the planning console
---
title: Create a parent-child relationship on the planning console
description: The WBS section of the planning console allows you to create parent-child relationships for new tasks or move around existing tasks in a new parent-child relationship. The position of a task in the hierarchy and the level of indentation determine the parent-child relationship it has with the tasks above or below it.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-management/t\_CreateParentChildRelatConsole.html
release: australia
product: Project Management
classification: project-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 2
breadcrumb: [Using Planning console - Legacy, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management]
---
# Create a parent-child relationship on the planning console
The WBS section of the planning console allows you to create parent-child relationships for new tasks or move around existing tasks in a new parent-child relationship. The position of a task in the hierarchy and the level of indentation determine the parent-child relationship it has with the tasks above or below it.
## Before you begin
Role required: it\_project\_manager
## About this task
In this example, the System Readiness Assessment task is a child of the Planning task because it is one level below the Planning task and is indented.
\[Omitted image "example\_parent-child-task.png"\] Alt text: Parent-child task example
## Procedure
1. Select a task in the WBS section of the planning console to highlight it.
2. Select a combination of any of the following icons to create the task and move it or move the other tasks to create the required hierarchy:
|Icon|Action|
|----|------|
|Add task above icon \(\[Omitted image "add\_task\_above.png"\] Alt text: Add task icon\)|Create a task above the highlighted task.|
|Add task below icon \(\[Omitted image "add\_task\_below.png"\] Alt text: Add task icon\)|Create a task below the highlighted task.|
|Indent icon \(\[Omitted image "demote\_icon.png"\] Alt text: Indent icon\)|Makes the highlighted task a child of the task above it.|
**Parent Topic:**[Using Planning console - Legacy](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/c_TheProjectPlanningConsole.md)
**Related topics**
[Open the project planning console]()
[Planning console tasks]()
[Client side planning console]()
[Gantt chart]()
[Predecessor dependencies in the planning console]()
[Custom columns in the planning console]()
[Create a dependency from the planning console]()
[Using Planning console - Legacy](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/c_TheProjectPlanningConsole.md)
| title | Create a parent-child relationship on the planning console |
| description | The WBS section of the planning console allows you to create parent-child relationships for new tasks or move around existing tasks in a new parent-child relationship. The position of a task in the hierarchy and the level of indentation determine the parent-child relationship it has with the tasks above or below it. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/australia/it-business-management/project-management/t\_CreateParentChildRelatConsole.html |
| release | australia |
| product | Project Management |
| classification | project-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 2 |
| breadcrumb | Using Planning console - LegacyUsing Project ManagementProject ManagementProject Portfolio ManagementStrategic Portfolio Management |