Create a project task in the project workbench
task australia Updated Sep 10, 2026 1 min read t_CreateProjTaskProjWorkbench.md
Create a project task for a waterfall phase.
Before you begin
Role required: it_project_manager
About this task
While creating a project task in the project workbench, the time constraint type is defaulted based on the project type.
- For a manual project, the default constraint is Start On and can't be changed.
- For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required.
- When the constraint is Start ASAP, the Planned start date is disabled.
- When you create an agile phase and associate a sprint, the task start date is set from the sprint start date. The constraint is set to Start On automatically.
Procedure
-
Select a waterfall phase in the project workbench timeline.
-
Select New in the detail view.
-
Fill out the Project Task form.
-
Select Submit.
Parent Topic:Managing Project workbench
Related topics
Open a project in the project workbench
Manage project stories in the project workbench
Create a story in the project workbench
58 lines · 2.1 KB
--- title: Create a project task in the project workbench description: Create a project task for a waterfall phase. locale: en-US canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-management/t\_CreateProjTaskProjWorkbench.html release: australia product: Project Management classification: project-management topic_type: task last_updated: "2026-09-10" reading_time_minutes: 1 breadcrumb: [Managing Project workbench, Using Project workbench - Legacy, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management] --- # Create a project task in the project workbench Create a project task for a waterfall phase. ## Before you begin Role required: it\_project\_manager ## About this task While creating a project task in the project workbench, the time constraint type is defaulted based on the project type. - For a manual project, the default constraint is Start On and can't be changed. - For an automatic project, the default constraint is Start ASAP and can be changed to Start On if required. - When the constraint is Start ASAP, the **Planned start date** is disabled. - When you create an agile phase and associate a sprint, the task start date is set from the sprint start date. The constraint is set to Start On automatically. ## Procedure 1. Select a waterfall phase in the project workbench timeline. 2. Select **New** in the detail view. 3. Fill out the Project Task form. 4. Select **Submit**. **Parent Topic:**[Managing Project workbench](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/c_UsingProjectWorkbench.md) **Related topics** [Open a project in the project workbench]() [Manage project stories in the project workbench]() [Create a story in the project workbench]() [Create a test case in the project workbench]() [Managing Project workbench](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-management/c_UsingProjectWorkbench.md)
| title | Create a project task in the project workbench |
| description | Create a project task for a waterfall phase. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/australia/it-business-management/project-management/t\_CreateProjTaskProjWorkbench.html |
| release | australia |
| product | Project Management |
| classification | project-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 1 |
| breadcrumb | Managing Project workbenchUsing Project workbench - LegacyUsing Project ManagementProject ManagementProject Portfolio ManagementStrategic Portfolio Management |