Assign a project schedule

task australia Updated Sep 15, 2026 4 min read t_UseAProjectSchedule.md
Raw file servicenow.com

Assign a schedule to a project so that task durations and dates reflect real working days and hours.

Before you begin

Role required: it_project_manager

A project uses a schedule to determine which days and hours count as working time. Without an assigned schedule, a project treats every day as a full 24 hours, which makes task durations and the finish date unrealistic. Assign a schedule to base the project on real working time. If the schedules in the base system don't fit your needs, define a new one.

Procedure

  1. Open a project.

  2. If the Default view is active, right-click the header bar and select View > Advanced.

  3. Select a schedule in the Schedule field and select Save.

Parent Topic:Starting a project

Related topics

Create a project task from a project

Create a parent-child relationship on the Project Task form

Create a monetary benefit plan for a project

Create a non-monetary benefit plan for a project

Associate monetary and non-monetary benefit plans

Create a project cost plan

Recalculating costs of all resource plans in a project

Create an expense line

Create and manage waterfall projects

Schedule a project from a start date

Apply or change a task constraint

Update a project

Copy a project

Create baseline of a project

Create a milestone

Activate project task email notifications

Change the planned start date of a project

Create a cost type definition

Costing add-on in Project Management

Generate labor costs

Create a project status report

Allocate budget to a project

Migrate budget of active projects to Next Experience

Migrate financial baselines of projects to Next Experience

Search documentation
Search document titles and file paths on the australia branch