Task link types

reference australia Updated Sep 10, 2026 1 min read task-link-types-project-management.md
Raw file servicenow.com

Task links define the dependency relationship between tasks. Linking tasks creates dependencies that affect task start and finish dates and determine the critical path. The following table describes the four supported link types.

Link type Abbreviation Description
Finish-to-Start FS Task B cannot start until Task A finishes.
Start-to-Start SS Task B cannot start until Task A starts.
Finish-to-Finish FF Task B cannot finish until Task A finishes.
Start-to-Finish SF Task B cannot finish until Task A starts.

Parent Topic:Project Management reference

Related topics

Schedule a project from a start date

Project scheduling in Project Management