Update task dependency details from Project Workspace
task australia Updated Sep 10, 2026 1 min read update-the-dependency-details-for-tasks-from-project-workspace.md
Update the details of the dependency including its type and lag time from Project Workspace.
Before you begin
Role required: it_project_manager
Procedure
-
Open a project from the home page of Project Workspace.
For information, see Access the Project Workspace.
-
Open the dependency side panel in one of the two ways.
Option Action From the data grid From the dependency column, select the dependency of the task. From the timeline view Select the dependency line. -
Edit the fields.
-
Select Update.
Parent Topic:Add internal project task dependencies from Project Workspace
43 lines · 1.7 KB
---
title: Update task dependency details from Project Workspace
description: Update the details of the dependency including its type and lag time from Project Workspace.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/project-workspace/update-the-dependency-details-for-tasks-from-project-workspace.html
release: australia
product: Project Workspace
classification: project-workspace
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 1
breadcrumb: [Add internal project task dependencies from Project Workspace, Manage projects, Project Workspace, Project Portfolio Management, Strategic Portfolio Management]
---
# Update task dependency details from Project Workspace
Update the details of the dependency including its type and lag time from Project Workspace.
## Before you begin
Role required: it\_project\_manager
## Procedure
1. Open a project from the home page of Project Workspace.
For information, see [Access the Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/access-new-project-workspace.md).
2. Open the dependency side panel in one of the two ways.
|Option|Action|
|------|------|
|**From the data grid**|From the dependency column, select the dependency of the task.|
|**From the timeline view**|Select the dependency line.|
3. Edit the fields.
4. Select **Update**.
**Parent Topic:**[Add internal project task dependencies from Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/create-dependencies-for-project-tasks-from-project-workspace.md)
| title | Update task dependency details from Project Workspace |
| description | Update the details of the dependency including its type and lag time from Project Workspace. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/australia/it-business-management/project-workspace/update-the-dependency-details-for-tasks-from-project-workspace.html |
| release | australia |
| product | Project Workspace |
| classification | project-workspace |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 1 |
| breadcrumb | Add internal project task dependencies from Project WorkspaceManage projectsProject WorkspaceProject Portfolio ManagementStrategic Portfolio Management |