Create resource assignments using Project Workspace
Create an attribute-based resource assignment in the Project Workspace application for any project or project task.
Before you begin
After a resource assignment is created, a Resource Plan is created automatically in the back-end. The resources are allocated to the project and approved by the Resource Manager. You can edit the assignment throughout the project life cycle.
Role required: it_project_manager
Procedure
-
Navigate to Workspaces > Project Workspace and open a project.
-
View the resource assignment pane by enabling the Resource assignments toggle button.
Note: If the sn_pw.enable_resource_planning property is set to true, then the Resource assignment toggle button and resource assignment pane are displayed in Project Workspace. The default value is false. You must have the pps_admin role to enable this property.
-
From the Planning pane, double-click the Resource assignees field for a project task.
You can assign the resources from both planning and resource assignment pane.
-
From the resource assignment pane, create a resource assignment for a project or task by selecting Add resource.
You can create a resource assignment for a project from the resource assignment pane only.
-
From the resource assignee list, select a user or group and press Enter.
When you create a resource assignment, the user or group allocation is based on the selected effort type. For example, when you add a user and the effort type is selected as hours, the allocations are displayed in hours.
A resource assignment record is created and auto-saved. The resource assignment form auto-populates the project or task information.
-
From the resource assignment pane, create a resource assignment for a project or task by selecting New Resource.
You can use this option to create a resource assignment using the resource form. On the New Resource Assignment form, fill in the fields and select Submit. For a description of the field names, see New Resource Assignment form.
What to do next
Update resource assignment from Project Workspace
Parent Topic:Manage resource assignments from Project Workspace
Related topics
Delete a resource assignment from Project Workspace
---
title: Create resource assignments using Project Workspace
description: Create an attribute-based resource assignment in the Project Workspace application for any project or project task.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/australia/it-business-management/resource-management/create-ra-pws-rmw.html
release: australia
product: Resource Management
classification: resource-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 2
breadcrumb: [Manage resource assignments from Project Workspace, Use, Resource Management Workspace, Project Portfolio Management, Strategic Portfolio Management]
---
# Create resource assignments using Project Workspace
Create an attribute-based resource assignment in the Project Workspace application for any project or project task.
## Before you begin
After a resource assignment is created, a Resource Plan is created automatically in the back-end. The resources are allocated to the project and approved by the Resource Manager. You can edit the assignment throughout the project life cycle.
Role required: it\_project\_manager
## Procedure
1. Navigate to **Workspaces** > **Project Workspace** and open a project.
2. View the resource assignment pane by enabling the **Resource assignments** toggle button.
**Note:** If the **sn\_pw.enable\_resource\_planning** property is set to true, then the **Resource assignment** toggle button and resource assignment pane are displayed in Project Workspace. The default value is false. You must have the pps\_admin role to enable this property.
3. From the Planning pane, double-click the **Resource assignees** field for a project task.
You can assign the resources from both planning and resource assignment pane.
4. From the resource assignment pane, create a resource assignment for a project or task by selecting **Add resource**.
You can create a resource assignment for a project from the resource assignment pane only.
5. From the resource assignee list, select a user or group and press **Enter**.
When you create a resource assignment, the user or group allocation is based on the selected effort type. For example, when you add a user and the effort type is selected as hours, the allocations are displayed in hours.
A resource assignment record is created and auto-saved. The resource assignment form auto-populates the project or task information.
6. From the resource assignment pane, create a resource assignment for a project or task by selecting **New Resource**.
You can use this option to create a resource assignment using the resource form. On the New Resource Assignment form, fill in the fields and select **Submit**. For a description of the field names, see [New Resource Assignment form](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/resource-management/create-ra-form-rmw.md).
## What to do next
[Update resource assignment from Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/update-resource-assignment-pw.md)
**Parent Topic:**[Manage resource assignments from Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/resource-management/use-ra-rmw.md)
**Related topics**
[Delete a resource assignment from Project Workspace](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/delete-resource-assignment-pw.md)
[Update the resource allocation in a heatmap](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/view-allocations-heatmap-prj-wksp.md)
[Realign resource assignment to project task](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/australia/markdown/australia/it-business-management/project-workspace/realign-resource-assignment-to-task.md)
| title | Create resource assignments using Project Workspace |
| description | Create an attribute-based resource assignment in the Project Workspace application for any project or project task. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/australia/it-business-management/resource-management/create-ra-pws-rmw.html |
| release | australia |
| product | Resource Management |
| classification | resource-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 2 |
| breadcrumb | Manage resource assignments from Project WorkspaceUseResource Management WorkspaceProject Portfolio ManagementStrategic Portfolio Management |