Change the time that an agent worked on a crew task
task brazil Updated Sep 10, 2026 1 min read change-agent-task-time.md
Update the time that an agent spent on a crew task if they spent more or less time on the task than the rest of the crew.
Before you begin
Role required: wm_admin, wm_manager, wm_dispatcher, wm_crew_moderator.
About this task
When you edit the Actual work start or Actual work end values, the Work duration and Actual work duration update for the agent.
Procedure
-
Navigate to All > Field Service > Manager > Work Order Tasks.
-
Select the complete work order task for which you want to change an agents time.
-
In the Task Assignees tab, select the Resource type on the name of the agent you want to edit the time worked for.
-
Update the Actual work start or Actual work end.
-
Select Update.
40 lines · 1.4 KB
--- title: Change the time that an agent worked on a crew task description: Update the time that an agent spent on a crew task if they spent more or less time on the task than the rest of the crew. locale: en-US canonical_url: https://www.servicenow.com/docs/r/field-service-management/field-service-manager-workforce/change-agent-task-time.html release: brazil product: Field Service Manager Workforce classification: field-service-manager-workforce topic_type: task last_updated: "2026-09-10" reading_time_minutes: 1 breadcrumb: [Using Crew operations, Managing workforce, Use, Field Service Management] --- # Change the time that an agent worked on a crew task Update the time that an agent spent on a crew task if they spent more or less time on the task than the rest of the crew. ## Before you begin Role required: wm\_admin, wm\_manager, wm\_dispatcher, wm\_crew\_moderator. ## About this task When you edit the Actual work start or Actual work end values, the Work duration and Actual work duration update for the agent. ## Procedure 1. Navigate to **All** > **Field Service** > **Manager** > **Work Order Tasks**. 2. Select the complete work order task for which you want to change an agents time. 3. In the **Task Assignees** tab, select the **Resource type** on the name of the agent you want to edit the time worked for. 4. Update the **Actual work start** or **Actual work end**. 5. Select **Update**.
| title | Change the time that an agent worked on a crew task |
| description | Update the time that an agent spent on a crew task if they spent more or less time on the task than the rest of the crew. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/field-service-management/field-service-manager-workforce/change-agent-task-time.html |
| release | brazil |
| product | Field Service Manager Workforce |
| classification | field-service-manager-workforce |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 1 |
| breadcrumb | Using Crew operationsManaging workforceUseField Service Management |