Create an issue to document policy, risk, or audit observations, or to accept any GRC problems. You can also identify the source of the issue to help analyze and classify the issues.

Before you begin

Role required: sn_audit.manager, sn_audit_ws.supervisor

Procedure

  1. Navigate to All > Audit > Audit Workspace.

  2. Click the lists icon ([Omitted image "ListsIcon.jpg"] Alt text: List icon.).

  3. Click All engagements or My engagements in the Execution list.

  4. Click the link to the engagement record in the Name column.

    The engagement record details open in the Overview tab.

  5. Click the Other issues related list.

  6. Click New.

  7. On the form, fill in the fields.

Field

Description

Number

Unique identification number.

Name

Name of the issue.

Issue source

Source from where the issue was created. This field is auto-populated with one of the following options based on how the issue is created:- Indicator Failure: Issue is created by a failure of the indicator.

  • Risk Assessment: Issue is created in a risk.
  • Risk Event: Issue is created in a risk event.
  • Control Attestation Failure: Issue is created due to a non-compliant control.
  • Control Test Failure: Issue is created when a control is ineffective and the control test is marked as closed and complete.
  • Ad-hoc: Issue is manually created.

Issue type

Type of issue.

Classification

Classification of the issue as a risk, compliance, or audit, based on the issue type.

State

  • New
  • Analyze
  • Respond
  • Review
  • Closed Complete
  • Closed Incomplete

Substate

Substate and applicable details for the substate.

Priority

Sequence in which an issue needs to be resolved, based on its impact and urgency:- 1 — Critical

  • 2 — High
  • 3 — Moderate
  • 4 — Low
  • 5 — Planning

Issue rating

Issue manager can assign a issue rating to the issue. Based on the issue rating, the Due date in the Dates tab is calculated as follows and displayed:- Very high (2 days)

  • High (4 days)
  • Moderate (8 days)
  • Low (10 days)
  • Very Low (15 days) You can manually override the Due date.

Description

Comprehensive description of the issue.

Assignment

Assignment group

Group to which the issue is assigned. Each member receives a notification when an activity occurs on this issue.

Assigned to

Member of the group assigned to resolve the issue.

Issue manager group

Group responsible for managing and reviewing the issue.

Issue manager

User responsible for managing and reviewing the issue.

Watch list

Users added to view the issue.

Schedule

Due date

Due date is auto-populated based on a GRC property, Auto populate due date based on issue rating. If it is set to Yes, the field is auto-populated based on the predefined remediation time frame for the issue's risk rating. Otherwise, you can manually enter a due date.When an issue transitions to the Respond state, an entry in this field is mandatory.

Confirmed date

Date on which the issue is confirmed. This field is read-only, and displays the current date when the issue is moved from New to any of the following states:- Analyze

  • Review
  • Respond Note: If a triage issue is converted to an actual issue, this field displays the date it was converted.

Created

Date and time the issue was created.

Closed

Date and time the issue was closed.

Planned start date

Date and time when the work on the issue is expected to begin.

Planned end date

Date and time when the work on the issue is expected to end.

Planned duration

Estimated duration of work time. Calculated using the Planned start date and Planned end date.

Actual start date

Time when work began on the issue.

Actual end date

Time when work on the issue was completed.

Actual duration

Duration of work time. Calculated using the Actual start date and Actual end date.

Details

Control/Risk

Control or risk associated with the issue.

Control Objective/Risk statement

Control objective or risk statement related to this issue.

Entity

Related entity.

Configuration item

Item associated with the issue. If all child issues have the same configuration item, it gets copied over to the parent issue.

Location

Location where the issue occurred.

Risk event

Related risk event.

Engagement

Related engagement.

Policy

Policy associated with the issue.

Authority document

Authority document associated with the issue.

Issue grouping

Parent issue

Parent issue to which the issue belongs.

Issue group rule

Group rule assigned to the issue.Issue group rule is used to group similar issues together into a parent issue based on conditions defined in the rule. This allows you to work on similar issues simultaneously and close out the parent issue after all issues are resolved. This closes out all the child issues.

Action plan

Recommendation

Resolution actions recommended by the risk, compliance, or audit teams.

Action plan

Plan for remediating the issue.

Confidentiality

Confidential

Option to enable confidentiality of the record. Only the assigned confidential users or confidential groups of users can access the record. For more information on confidential option, see Confidentiality flag for audit and compliance records.

Activity

Work notes (Private)

Information about how to resolve the issue, or steps already taken to resolve it, if applicable. Work notes are visible to users who are assigned to the issue.

Additional comments

Public information about the issue.

8. Click **Save**.