Create a milestone for an engagement

task brazil Updated Sep 10, 2026 2 min read create-milestone-engagmt-audit-ws.md
Raw file servicenow.com

Create a milestone for an engagement to track the progress of an engagement. You can also add audit tasks to a milestone.

Before you begin

Role required: sn_audit.manager, sn_audit_ws.supervisor

About this task

A milestone is used to track the progress of an engagement.

After you create milestones for an engagement, you can also add audit tasks to the milestone. You can track those tasks as milestones.

You can assign a milestone to a user who is responsible for the milestone. The assigned user must have the sn_audit.user role. The assigned user then receives a notification about the assignment.

If an engagement moves to the Follow Up state, it can automatically close. The engagement moves to the Closed state when there are no open audit tasks, open milestones, or open observations.

Procedure

  1. Navigate to All > Audit > Audit Workspace.

  2. Select the lists icon ([Omitted image "ListsIcon.jpg"] Alt text: List icon.).

  3. Select All engagements or My engagements in the Execution list.

  4. Select the link to the engagement record in the Name column.

  5. Select the Milestones tab.

  6. Select New.

  7. On the form, fill in the fields.

Field

Description

Number

Unique number of the milestone. This number is automatically generated.

Name

Name of the milestone.

Parent

Parent engagement of the milestone.

Type

Audit milestone type. The choices are:- Scoping

  • Planning
  • Fieldwork
  • Follow up
  • Reporting
  • Closure

State

State of the milestone. The default state is Open.

Percent complete

Percentage of milestone completed.When a value is entered in this field, the state changes to Work in progress.

Key milestone

Option to mark the milestone as important.

Auto complete and close

Option to mark the milestone as close complete when all the associated audit tasks are completed and closed.If this option is enabled, then the percent complete is automatically updated according to the number of tasks marked as closed complete.

Description

Brief description of the milestone.

Assignment

Assignment group

Group responsible for the milestone.The group members must have the sn_audit.user role assigned.

Assigned to

Person responsible for working on the milestone.

Schedule

Due date

Expected completion date of the milestone.

Completion date

Actual completion date of the milestone.

Closed date

Actual close date of the milestone.

Activity

Additional comments

Comments that customers can also view.

Work notes (Private)

Comments that only the administrator and audit supervisor can view.

8. Select **Save**.
You can view the description of the Milestone record and monitor its status in the **State** banner of the default Overview page.