Create a control test from an engagement

task brazil Updated Sep 10, 2026 5 min read t_CreateControlTest.md
Raw file servicenow.com

After defining a control, audit managers create control tests that run periodically and provide documented evidence of whether the associated control is operating correctly. After creating multiple control tests on an engagement, use the Control tests grid to view, manage, and request evidence for all tests in one place.

Before you begin

Role required: sn_audit.admin and sn_audit.manager

Starting with Audit Management 23.x.x, you can store supporting documents in Microsoft Word or PDF formats on evidence, engagement, and control test records. Use the ServiceNow Otto® panel to ask questions or summarize documents. Use voice assist to enable voice chat and audio summaries. For more information, see Using Document Management System in Audit Workspace.

Procedure

  1. Navigate to All > Audit > Engagements > All Engagements.

  2. Open the engagement for the audit task you want to create.

    Assign audit tasks to engagement in one of the following states:

    • Validate
    • Fieldwork
    • Awaiting approval
  3. In the Audit Tasks Related List, click New.

  4. In the Audit Tasks Interceptor, click Control Test.

  5. On the form, fill in the fields.

Field

Description

Number

Unique identification number.

State

  • Open
  • Work in Progress
  • Review
  • Closed Complete
  • Closed Incomplete
  • Closed Skipped

Parent

Parent audit task.

Control effectiveness

Control effectiveness.

Assigned to

User assigned to this control test.

Issue

Issue related to this control test.

Test plan

Test plan associated with this control test.

Short description

Brief description of the control test.

Schedule

Planned start date

Intended date the control test should begin.

Planned end date

Intended date the control test should end.

Planned duration

Expected duration of this control test. As with actual duration, the planned duration shows total activity time and takes the control test schedule into consideration.

Actual start date

Date that this control test began.

Actual end date

Date that this control test ended.

Actual duration

Duration of the control test from control test start to control test closure.

Design test

Design effectiveness

  • Effective
  • Ineffective
  • None: Default value; to be populated after design testing is complete

Design expectations

Basic requirement that should be met by a control so that it is effective. This checks if the control was designed properly to achieve the control objective.

Design assessment procedures

Procedure or steps to be followed to conclude whether the design of the control is effective to achieve the control objective or not. This is based on the design expectation.

Design results

Results of testing the design of the control based on the design assessment procedure.

Operation test

Operation effectiveness

  • Effective
  • Ineffective
  • None: Default value; to be populated after design testing is complete

Operation expectations

Expectations that should be met to ensure that the control is operating effectively to achieve the control objective.

Operation assessment procedures

Detailed steps, to carry out the operation expectations, which need to be performed to conclude that the control is operating successfully.

Operation results

Results of testing the operation of the control based on the operation assessment procedure.

Activity journal

Work notes

Comments that are viewable by the audit manager.

Additional comments

Customer-viewable comments.

Confidentiality

Confidential

Option to enable confidentiality of the record. Only the assigned confidential users or confidential groups of users can access the record.For more information on confidential option, see Confidentiality flag for audit and compliance records.

The control test form captures two types of testing:
-   Design Test: Validates whether the control was designed properly to achieve the control objective. Set Design effectiveness to Effective or Ineffective based on design assessment procedures and results.
-   Operational Test: Validates whether the control is operating effectively in practice. Set Operation effectiveness to Effective or Ineffective based on operational assessment procedures and results.
Both sections capture expectations, assessment procedures, and results to provide documented evidence of control effectiveness.

**Note:** After you create the control test and assign it to a user, that assigned user can edit the Design results and Operational results fields. Other fields are editable only by users with sn\_audit.admin or sn\_audit.manager roles.
  1. Click Submit.

  2. Attach a document with the record in the Document panel.

  3. Ask questions about the document in the ServiceNow Otto® panel.

  4. Use voice assist to navigate documents with voice commands and receive audio summaries.

Result

After creating the control test, you can:

  • View in grid: Use the Control tests tab on the engagement record to view all control tests in a single grid without opening individual records. For information, see View control tests in a grid on an engagement.
  • Request evidence: Select Request evidence directly from the grid to collect evidence from the assigned auditor.
  • Personalize columns: Show or hide additional columns such as Reference and Implementation Statement through column personalization settings.
  • Use Hierarchical view: Switch to Hierarchical view for a tree-structured layout of control tests and related audit tasks.

What to do next

Beginning with 23.x.x release, the control test form also has a Documents panel in addition to the Attachments panel. You can add, version, and manage permissions on documents while the control test is not in a Closed Complete, Closed Incomplete, or Closed Skipped state. For more information, see Using Document Management System in Audit Workspace.

Parent Topic:Manage engagements

Search documentation