Add change requests for a demand

task brazil Updated Sep 10, 2026 1 min read add-change-requests-for-a-demand-ppw.md
Raw file servicenow.com

Add a change request as the outcome of an action taken to resolve an issue or mitigate a risk. The change request can affect the demand's scope, resource requirements, cost, or schedule.

Before you begin

Role required: it_demand_manager

Procedure

  1. Navigate to Workspaces > Portfolio Planning Workspace.

  2. Select the Demands icon [Omitted image "demands-icon.png"].

  3. Open a demand from the List page.

  4. Select Details from the navigation menu.

  5. Select the Request Changes tab.

    Note: If the Request Changes tab isn't visible, select More > Request Changes.

  6. Select New.

  7. On the Request Change form, fill in the fields.

    For a description of the field values, see Request change form.

  8. Select Save.