Predecessor dependencies in the planning console
In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values.
The Predecessor column on the planning console can specify dependencies between tasks. The values that you put in this column must be in the following format:
{WBS_number}{dependency_type}+{lag_time}
Where
WBS_numberis the number of the predecessor task in the relationship.dependency_typeis one of the types of dependencies that the application supports.lag_timeis the amount of time, in days, to delay the start of the dependent task. This value can be positive or negative integers.
The values are entered without the curly braces {}. See the examples in the table.
Note: You can also edit tasks from the Gantt chart by clicking the relationship line. See Gantt chart options and Modify a project task dependency for details.
| Dependency type | Example | Additional information |
|---|---|---|
| Finish to start | 1.1fs+0 | The task you are editing starts when task 1.1 is finished. |
| Start to start | 1.1ss+0 | Task 1.1 cannot finish until the task you are editing finishes. |
| Start to finish | 1.1sf+0 | Task 1.1 cannot start until the task you are editing finishes. |
| Finish to finish | 1.1ff+0 | The task you are editing cannot finish until task 1.1 finishes. |
Parent Topic:Using Planning console - Legacy
Related topics
Open the project planning console
Create a parent-child relationship on the planning console
Custom columns in the planning console
---
title: Predecessor dependencies in the planning console
description: In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/it-business-management/project-management/r\_ProjectTaskDependencyValues.html
release: brazil
product: Project Management
classification: project-management
topic_type: reference
last_updated: "2026-09-10"
reading_time_minutes: 2
breadcrumb: [Using Planning console - Legacy, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management]
---
# Predecessor dependencies in the planning console
In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values.
The **Predecessor** column on the planning console can specify dependencies between tasks. The values that you put in this column must be in the following format:
`{WBS_number}{dependency_type}+{lag_time}`
Where
- `WBS_number` is the number of the predecessor task in the relationship.
- `dependency_type` is one of the [types of dependencies](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/c_ParentChildRollupTaskCalcs.md) that the application supports.
- `lag_time` is the amount of time, in days, to delay the start of the dependent task. This value can be positive or negative integers.
The values are entered without the curly braces \{\}. See the examples in the table.
**Note:** You can also edit tasks from the Gantt chart by clicking the relationship line. See [Gantt chart options](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/r_EditTasks.md) and [Modify a project task dependency](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_ModifyProjectTaskDependencies.md) for details.
|Dependency type|Example|Additional information|
|---------------|-------|----------------------|
|Finish to start|**1.1fs+0**|The task you are editing starts when task 1.1 is finished.|
|Start to start|**1.1ss+0**|Task 1.1 cannot finish until the task you are editing finishes.|
|Start to finish|**1.1sf+0**|Task 1.1 cannot start until the task you are editing finishes.|
|Finish to finish|**1.1ff+0**|The task you are editing cannot finish until task 1.1 finishes.|
**Parent Topic:**[Using Planning console - Legacy](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/c_TheProjectPlanningConsole.md)
**Related topics**
[Open the project planning console]()
[Planning console tasks]()
[Client side planning console]()
[Gantt chart]()
[Create a parent-child relationship on the planning console]()
[Custom columns in the planning console]()
[Create a dependency from the planning console]()
[Using Planning console - Legacy](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/c_TheProjectPlanningConsole.md)
| title | Predecessor dependencies in the planning console |
| description | In the WBS section of the planning console, you can create dependencies between tasks by specifying a series of values. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/project-management/r\_ProjectTaskDependencyValues.html |
| release | brazil |
| product | Project Management |
| classification | project-management |
| topic_type | reference |
| last_updated | 2026-09-10 |
| reading_time_minutes | 2 |
| breadcrumb | Using Planning console - LegacyUsing Project ManagementProject ManagementProject Portfolio ManagementStrategic Portfolio Management |