Update task dependency details from Project Workspace

task brazil Updated Sep 10, 2026 1 min read update-the-dependency-details-for-tasks-from-project-workspace.md
Raw file servicenow.com

Update the details of the dependency including its type and lag time from Project Workspace.

Before you begin

Role required: it_project_manager

Procedure

  1. Open a project from the home page of Project Workspace.

    For information, see Access the Project Workspace.

  2. Open the dependency side panel in one of the two ways.

    Option Action
    From the data grid From the dependency column, select the dependency of the task.
    From the timeline view Select the dependency line.
  3. Edit the fields.

  4. Select Update.

Parent Topic:Add internal project task dependencies from Project Workspace