Recalculate costs of a resource plan of a project or demand
Recalculate the resource costs of an individual resource plan for a project or demand whenever the hourly rates change in the associated rate model.
Before you begin
Ensure the following setup:
- The project or demand must have an active rate model assigned.
- The resource plan must be in either Planned, Requested, Confirmed, or Allocated states.
Role required: resource_manager
About this task
To update the costs of all the resource plans of a project or demand in one go, you can use the Recalculate Resource Costs option from the project form or demand form.
Procedure
-
To open a resource plan of a project or demand, perform one of the following actions.
- Navigate to Project > Projects > All, and open a project.
- Navigate to Demand > Demands > All, and open a demand.
-
From the Resource Plans related list, open a resource plan for which you want to recalculate the costs.
-
On the Resource Plan form, select the Recalculate Resource Cost related link.
-
In the Recalculate Resource Costs dialog box, specify the recalculation period in the Start date and End date fields.
By default, the Start date field has the current date and the End date field has the end date of the resource plan.
-
To recalculate the planned cost, select the Include planned costs option.
The Include planned costs option is available for a resource plan in the Confirmed or Allocated state. The option isn’t selected by default.
-
Select OK.
Result
- Recalculates the selected resource costs based on the latest hourly rates derived from the rate model associated with the project or demand.
- Updates the recalculated resource costs on the respective cost fields on the resource plan form and the Resource Plans related list of the associated project or demand.
- Reflects the revised values on the respective cost fields of associated project or demand.
Parent Topic:Resource plans
Related topics
Use Resource Finder to analyze resource availability
Create an operational resource plan
Confirm and allocate a resource plan
Request a change to a resource plan
Update cost plan related to a resource plan
Request extension of an allocated resource plan
Allocate resources for the extended period
---
title: Recalculate costs of a resource plan of a project or demand
description: Recalculate the resource costs of an individual resource plan for a project or demand whenever the hourly rates change in the associated rate model.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/it-business-management/resource-management/recalculate-resource-costs.html
release: brazil
product: Resource Management
classification: resource-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 4
breadcrumb: [Resource plans, Resource Management classic, Project Portfolio Management, Strategic Portfolio Management]
---
# Recalculate costs of a resource plan of a project or demand
Recalculate the resource costs of an individual resource plan for a project or demand whenever the hourly rates change in the associated rate model.
## Before you begin
Ensure the following setup:
- The project or demand must have an active rate model assigned.
- The resource plan must be in either Planned, Requested, Confirmed, or Allocated states.
Role required: resource\_manager
## About this task
To update the costs of all the resource plans of a project or demand in one go, you can use the **Recalculate Resource Costs** option from the [project form](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/recalculate-resource-costs-of-a-project.md) or [demand form](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/demand-management/recalculate-resource-costs-of-a-demand.md).
## Procedure
1. To open a resource plan of a project or demand, perform one of the following actions.
- Navigate to **Project** > **Projects** > **All**, and open a project.
- Navigate to **Demand** > **Demands** > **All**, and open a demand.
2. From the **Resource Plans** related list, open a resource plan for which you want to recalculate the costs.
3. On the Resource Plan form, select the **Recalculate Resource Cost** related link.
4. In the Recalculate Resource Costs dialog box, specify the recalculation period in the **Start date** and **End date** fields.
By default, the **Start date** field has the current date and the **End date** field has the end date of the resource plan.
5. To recalculate the planned cost, select the **Include planned costs** option.
The **Include planned costs** option is available for a resource plan in the Confirmed or Allocated state. The option isn’t selected by default.
6. Select **OK**.
## Result
- Recalculates the selected resource costs based on the latest hourly rates derived from the rate model associated with the project or demand.
- Updates the recalculated resource costs on the respective cost fields on the resource plan form and the **Resource Plans** related list of the associated project or demand.
- Reflects the revised values on the respective cost fields of associated project or demand.
**Parent Topic:**[Resource plans](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/resource-management/c_ResourcePlans.md)
**Related topics**
[Create a resource plan]()
[Use Resource Finder to analyze resource availability]()
[Create an operational resource plan]()
[Request resources]()
[Confirm a resource plan]()
[Confirm and allocate a resource plan]()
[Request a change to a resource plan]()
[Update cost plan related to a resource plan]()
[Complete a resource plan]()
[Cancel a resource plan]()
[Delete a resource plan]()
[Extend a resource plan]()
[Request extension of an allocated resource plan]()
[Allocate resources for the extended period]()
[Reduce the duration of a resource plan]()
[Time zones in resource plans]()
[Associate a time card with a resource plan]()
| title | Recalculate costs of a resource plan of a project or demand |
| description | Recalculate the resource costs of an individual resource plan for a project or demand whenever the hourly rates change in the associated rate model. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/resource-management/recalculate-resource-costs.html |
| release | brazil |
| product | Resource Management |
| classification | resource-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 4 |
| breadcrumb | Resource plansResource Management classicProject Portfolio ManagementStrategic Portfolio Management |