Update cost plan related to a resource plan
If a resource plan is associated to a project, project task, or demand and has a related cost plan. Then, a requester or a resource manager can update the related cost plan after updating the resource plan.
Before you begin
Role required: resource_user or resource_manager or it_project_manager or it_demand_manager
About this task
If a resource plan does not have a related cost plan, the Update Cost Plan related link is not displayed for the resource plan.
Procedure
-
Save the updates to the resource plan.
-
Click the Update Cost Plan related link.
The cost plan associated to a resource plan is automatically updated as soon as the Planned cost in the resource plan is updated. The planned cost on resource plan gets updated when there is a change in:
- Planned hours
- User
- State
- Start and end dates
Result
The cost plan associated to the resource plan is updated as follows:
- If the resource plan is in Planning or Requested state, planned hours is updated in the cost plan.
- If the resource plan is in Confirmed/Allocated state and the Confirmed/Allocated hours are less than planned hours. Then, the higher of the planned cost and Confirmed/Allocated cost is updated in the cost plan.
- If the resource plan is in Confirmed/Allocated state and the Confirmed/Allocated hours are equal to or more than planned hours. Then, the Confirmed/Allocated cost is updated in the cost plan.
Cost from resource plan will be interfaced to the unit_cost field on the Cost Plan [cost_plan] table.
Parent Topic:Resource plans
Related topics
Use Resource Finder to analyze resource availability
Create an operational resource plan
Confirm and allocate a resource plan
Request a change to a resource plan
Recalculate costs of a resource plan of a project or demand
Request extension of an allocated resource plan
Allocate resources for the extended period
---
title: Update cost plan related to a resource plan
description: If a resource plan is associated to a project, project task, or demand and has a related cost plan. Then, a requester or a resource manager can update the related cost plan after updating the resource plan.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/it-business-management/resource-management/t\_UpdateRelatedCostPlan.html
release: brazil
product: Resource Management
classification: resource-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 3
breadcrumb: [Resource plans, Resource Management classic, Project Portfolio Management, Strategic Portfolio Management]
---
# Update cost plan related to a resource plan
If a resource plan is associated to a project, project task, or demand and has a related cost plan. Then, a requester or a resource manager can update the related cost plan after updating the resource plan.
## Before you begin
Role required: resource\_user or resource\_manager or it\_project\_manager or it\_demand\_manager
## About this task
If a resource plan does not have a related cost plan, the **Update Cost Plan** related link is not displayed for the resource plan.
## Procedure
1. Save the updates to the resource plan.
2. Click the **Update Cost Plan** related link.
The cost plan associated to a resource plan is automatically updated as soon as the **Planned cost** in the resource plan is updated. The planned cost on resource plan gets updated when there is a change in:
- Planned hours
- User
- State
- Start and end dates
## Result
The cost plan associated to the resource plan is updated as follows:
- If the resource plan is in Planning or Requested state, planned hours is updated in the cost plan.
- If the resource plan is in Confirmed/Allocated state and the Confirmed/Allocated hours are less than planned hours. Then, the higher of the planned cost and Confirmed/Allocated cost is updated in the cost plan.
- If the resource plan is in Confirmed/Allocated state and the Confirmed/Allocated hours are equal to or more than planned hours. Then, the Confirmed/Allocated cost is updated in the cost plan.
Cost from resource plan will be interfaced to the unit\_cost field on the Cost Plan \[cost\_plan\] table.
**Parent Topic:**[Resource plans](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/resource-management/c_ResourcePlans.md)
**Related topics**
[Create a resource plan]()
[Use Resource Finder to analyze resource availability]()
[Create an operational resource plan]()
[Request resources]()
[Confirm a resource plan]()
[Confirm and allocate a resource plan]()
[Request a change to a resource plan]()
[Recalculate costs of a resource plan of a project or demand]()
[Complete a resource plan]()
[Cancel a resource plan]()
[Delete a resource plan]()
[Extend a resource plan]()
[Request extension of an allocated resource plan]()
[Allocate resources for the extended period]()
[Reduce the duration of a resource plan]()
[Time zones in resource plans]()
[Associate a time card with a resource plan]()
| title | Update cost plan related to a resource plan |
| description | If a resource plan is associated to a project, project task, or demand and has a related cost plan. Then, a requester or a resource manager can update the related cost plan after updating the resource plan. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/resource-management/t\_UpdateRelatedCostPlan.html |
| release | brazil |
| product | Resource Management |
| classification | resource-management |