Create a baseline

concept brazil Updated Sep 10, 2026 1 min read c_CreateABaseline.md
Raw file servicenow.com

A Planned Task Baseline is a record of the start and end times of the planned task at a particular moment in time.

To create a baseline, navigate to the form of the top planned task and select the Create a Baseline related link:

[Omitted image "PTBaseline.png"] Alt text: Create baseline for the current task.

To view the baseline, configure the related lists to add a related list of baselines:

[Omitted image "PTBaseline2.png"] Alt text: Baseline related list

The baseline can be viewed on a Gantt Chart using the related link.