Configure rollup for planned task fields

task brazil Updated Sep 10, 2026 1 min read t_ConfiguringRollupForPlannedTask.md
Raw file servicenow.com

You can configure the planned task fields to roll up the field values in the parent entity.

Before you begin

Role required: admin

About this task

By default the following fields are configured to roll up for any planned task and planned task derivatives:

Cost, Budget, Effort, Actual date, Planned date, Duration, Percent Complete

Procedure

  1. Navigate to All > System Definition > Tables.

  2. Open the Planned task rollup table.

  3. In the Related links, click Show List.

  4. Click New.

  5. Fill out the Planned task rollup form (see table).

  6. Click Submit.

Field

Description

Child

Select the table you want to include or exclude.

Field

Select the column name you want to include or exclude.

Navigator

The reference column of the parent to which the value must be rolled up.

Parent

Select the parent table.

Application

Auto-generated value.

Rollup

Select the check box to allow roll up. Leave the field unchecked to exclude the field from rollup.