Allocate budget to a project
Set the budget of a project according to the fiscal years.
Before you begin
Role required: it_portfolio_manager
Procedure
-
Open the project form.
-
In the related links, select Project Budget.
The Project Budget dialog box opens.
-
Select the fiscal year for which you want to set the budget for the project.
-
Enter the amounts for Capex Budget and Opex Budget.
The Total Budget is updated with the sum of capex and opex amounts.
-
Select OK.
- If the project does not have any cost plan associated, then project budget is distributed by honoring planned start and end dates of the project.
- If the project has any cost plan associated, then project budget is distributed by honoring the cost plan fiscal periods. Note: Negative budget amounts are supported. If you enter a negative Capex Budget or Opex Budget amount, or the associated cost plan has a negative total planned cost, the project budget is still distributed across the cost plan breakdowns and rolled up to the project financials.
Result
The project budget for the selected year appears in the Project Budget related list. You can select the amounts in the list to revise them.
Parent Topic:Starting a project
Related topics
Create a project task from a project
Create a parent-child relationship on the Project Task form
Create a monetary benefit plan for a project
Create a non-monetary benefit plan for a project
Associate monetary and non-monetary benefit plans
Recalculating costs of all resource plans in a project
Create and manage waterfall projects
Schedule a project from a start date
Apply or change a task constraint
Activate project task email notifications
Change the planned start date of a project
Costing add-on in Project Management
Create a project status report
---
title: Allocate budget to a project
description: Set the budget of a project according to the fiscal years.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/it-business-management/project-management/allocate-budget-to-project.html
release: brazil
product: Project Management
classification: project-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 5
breadcrumb: [Starting a project, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management]
---
# Allocate budget to a project
Set the budget of a project according to the fiscal years.
## Before you begin
Role required: it\_portfolio\_manager
## Procedure
1. Open the project form.
2. In the related links, select **Project Budget**.
The **Project Budget** dialog box opens.
3. Select the fiscal year for which you want to set the budget for the project.
4. Enter the amounts for **Capex Budget** and **Opex Budget**.
The **Total Budget** is updated with the sum of capex and opex amounts.
5. Select **OK**.
- If the project does not have any cost plan associated, then project budget is distributed by honoring planned start and end dates of the project.
- If the project has any cost plan associated, then project budget is distributed by honoring the cost plan fiscal periods.
**Note:** Negative budget amounts are supported. If you enter a negative **Capex Budget** or **Opex Budget** amount, or the associated cost plan has a negative total planned cost, the project budget is still distributed across the cost plan breakdowns and rolled up to the project financials.
## Result
The project budget for the selected year appears in the **Project Budget** related list. You can select the amounts in the list to revise them.
**Parent Topic:**[Starting a project](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_CreateAProject.md)
**Related topics**
[Create a project task from a project]()
[Create a parent-child relationship on the Project Task form]()
[Create a monetary benefit plan for a project]()
[Create a non-monetary benefit plan for a project]()
[Associate monetary and non-monetary benefit plans]()
[Create a project cost plan]()
[Recalculating costs of all resource plans in a project]()
[Create an expense line]()
[Create and manage waterfall projects]()
[Schedule a project from a start date]()
[Apply or change a task constraint]()
[Update a project]()
[Copy a project]()
[Assign a project schedule]()
[Create baseline of a project]()
[Create a milestone]()
[Activate project task email notifications]()
[Change the planned start date of a project]()
[Create a cost type definition]()
[Costing add-on in Project Management]()
[Generate labor costs]()
[Create a project status report]()
[Migrate budget of active projects to Next Experience]()
[Migrate financial baselines of projects to Next Experience]()
| title | Allocate budget to a project |
| description | Set the budget of a project according to the fiscal years. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/project-management/allocate-budget-to-project.html |
| release | brazil |
| product | Project Management |
| classification | project-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 5 |
| breadcrumb | Starting a projectUsing Project ManagementProject ManagementProject Portfolio ManagementStrategic Portfolio Management |