Starting a project

task brazil Updated Sep 8, 2026 6 min read t_CreateAProject.md
Raw file servicenow.com

Initiate a project by changing the project state to Work in Progress. Define important aspects of your Agile, Waterfall, or Hybrid project such as the duration, estimated cost, and net value to your organization to efficiently track the project's progress.

Before you begin

Role required: it_project_manager

About this task

When you change the State field on the Project form to Work in Progress, the Actual start date of the project changes to the planned start date.

You can create a project from the Projects list or from the Project Workspace. You must have the Agile Development 2.0 plugin to create an Agile or Hybrid project and the Test Management plugin to create a test phase for your project.

Note: You can also create a project from the demand workbench.

After you start the project:

  • The read-only Actual start date field of the project is populated with the planned date.

  • If a task or set of tasks are scheduled to start immediately upon project start, their actual start dates also get populated with the planned date. This applies when their time constraints are set to Start ASAP and they have no other start dependencies.

  • The planned start dates of all other tasks adjust accordingly based on the time you started the project. Their new planned start dates depend on several factors, including dependent relationships with other tasks and the duration for each task.

    Note: Once a project is in the Work in Progress state, it does not mean that the state of every task will start updating automatically based on planned start date. Other than the project tasks that you schedule to start ASAP when the project starts, project tasks aren't started automatically. Continue to manage the project and change the state of each task to Work in Progress.

You can also use the multi-currency feature to create a project in a local currency different from your functional currency. You must enable the PPM Standard Multicurrency plugin (com.snc.ppm_multicurrency) and switch to the Project Currency view for the additional fields in the Financials tab of the Project form. For more information, see Multi-currency in project financials.

Procedure

  1. Create a project in any of the following ways.

Location

Steps

From the Projects list

  1. Navigate to All > Project > Projects > All.
  2. In the Project list, select New. New.

From the project workspace

  1. Navigate to All > Project > Projects > Project Workspace.

Note: Starting with Brazil release, Project Workspace opens in Next Experience view.

  1. Select New Project.
  2. In the Create a project modal, fill in the details and select Confirm.
2. On the form, fill in the fields.
For field information, see [Project form](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/create-a-project-form.md).
  1. Select Submit.
  • Create a project task from a project
    Create tasks from the project form to break down project objectives into manageable units of work.
  • Create a parent-child relationship on the Project Task form
    Create a child task from any project task form.
  • Create a monetary benefit plan for a project
    Create a monetary benefit plan to specify the estimated benefit in a category spanning one or more fiscal periods. Project benefit plans capture the potential benefits accrued by the project when the project is executed.
  • Create a non-monetary benefit plan for a project
    Create a non-monetary benefit plan to specify the estimated benefit in a category spanning one or more fiscal periods. Project benefit plans capture the potential non-financial benefits accrued by the project when the project is executed.
  • Associate monetary and non-monetary benefit plans
    Associate monetary and non-monetary benefit plans, so that you can capture the potential benefits (financial and non-financial) accrued by the project for the hybrid benefit plans.
  • Create a project cost plan
    Create a cost plan to specify the unit cost of a cost type for a fiscal period. Project cost plans capture the costs of projects.
  • Recalculating costs of all resource plans in a project
    Recalculate resource costs for all resource plans in a project when hourly rates change in the associated rate model.
  • Create an expense line
    A project expense line is cost associated with a specific source, such as a user, fixed asset, or a CI. Expense lines are part of project cost plans.
  • Create and manage waterfall projects
    Plan, create, and manage projects using the Waterfall methodology.
  • Schedule a project from a start date
    Schedule a project from a start date and plan tasks and milestones based on your project requirements.
  • Apply or change a task constraint
    Apply a constraint to control when an automatically scheduled task starts or finishes. Set the constraint type and the associated constraint date if required.
  • Update a project
    Update the project and make adjustments in fields to handle scope, cost, and schedule. While a project is underway, keep actual values as current as possible. Continue to measure actual values, analyze the impact of any potential project risks.
  • Copy a project
    Another option for creating a project is to copy an existing project with all its tasks and relationships. After you specify the start date for the copy, the system adjusts all task start and end dates automatically.
  • Assign a project schedule
    Assign a schedule to a project so that task durations and dates reflect real working days and hours.
  • Create baseline of a project
    Create a schedule baseline and financial baseline of a project. A schedule baseline captures planned dates of all tasks and milestones at a particular moment in time. A financial baseline captures benefit and financial metric information (snapshot of cost plan, benefit plan, and project-level financial metrics) at a particular moment in time.
  • Create a milestone
    A milestone is a project task with a duration of zero (0). Use milestones to mark key dates in your project, such as key decision points, approvals, and holidays. Milestones are treated like any other project task and you can create dependencies between tasks and milestones.
  • Activate project task email notifications
    The following email notifications for the Project Management application are available by default, but are inactive. You must activate them manually.
  • Change the planned start date of a project
    Adjust the schedule of a project by changing the planned start date of a project and shifting it later or earlier than the current planned schedule.
  • Create a cost type definition
    Create a cost type definition to associate a cost type, operating, or capital, to an account in the General Ledger from the Financial Management application. Create a cost type definition if you are using Project Portfolio Management with Financials.
  • Costing add-on in Project Management
    The Project Management costing add-on connects the Project Management application to the Cost Management application to allow for estimating and tracking the costs associated with projects.
  • Generate labor costs
    Generate labor costs based on the planning attributes configured for financials in the planning attributes page for the resource assignments in a project.
  • Create a project status report
    Create project status report from the related lists of the project form. The project status report created for the most recent status date updates the status of the project in portfolios.
  • Allocate budget to a project
    Set the budget of a project according to the fiscal years.
  • Migrate budget of active projects to Next Experience
    Migrate the project budget to Next Experience to manage the financials using Project Workspace.
  • Migrate financial baselines of projects to Next Experience
    Migrate the financial baselines of your project to Next Experience to manage the financial using Project Workspace.

Parent Topic:Using Project Management

Related topics

Project form

Schedule a project from a start date

Project Portfolio Management