Create a dependency from the planning console
Create a dependency between two tasks on the planning console.
Before you begin
Role required: it_project_manager
About this task
You can create any type of dependency. See Parent-child rollup task calculations for an explanation of each type.
You can also create dependencies by using the Predecessor column on the Planning Console. See Predecessor dependencies in the planning console for more information.
Procedure
-
Select a task on the Gantt chart portion of the planning console.
A white circle appears on either end of the task, one at the start of the task and the other at the end of the task.
-
To create a dependency, select one of the white circles and drag it to the start or end of another task.
-
Double-click the dependency line to see the dependency on the Planned Task Relationship form.
-
Confirm that your dependency is correct.
You can make changes to the dependency as needed.
- Add an external dependency on planning console
Add an external dependency between two projects on the planning console. Use the work breakdown structure (WBS) column of the planning console to create a dependency between the different projects tasks. - Modify a project task dependency
Modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time. - Remove a dependency
Use the planning console to remove a dependency that is no longer necessary.
Parent Topic:Using Planning console - Legacy
Related topics
Open the project planning console
Create a parent-child relationship on the planning console
Predecessor dependencies in the planning console
---
title: Create a dependency from the planning console
description: Create a dependency between two tasks on the planning console.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/it-business-management/project-management/t\_CreateADependency.html
release: brazil
product: Project Management
classification: project-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 2
breadcrumb: [Using Planning console - Legacy, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management]
---
# Create a dependency from the planning console
Create a dependency between two tasks on the planning console.
## Before you begin
Role required: it\_project\_manager
## About this task
You can create any type of dependency. See [Parent-child rollup task calculations](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/c_ParentChildRollupTaskCalcs.md) for an explanation of each type.
You can also create dependencies by using the Predecessor column on the Planning Console. See [Predecessor dependencies in the planning console](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/r_ProjectTaskDependencyValues.md) for more information.
## Procedure
1. Select a task on the Gantt chart portion of the planning console.
A white circle appears on either end of the task, one at the start of the task and the other at the end of the task.
2. To create a dependency, select one of the white circles and drag it to the start or end of another task.
3. Double-click the dependency line to see the dependency on the Planned Task Relationship form.
4. Confirm that your dependency is correct.
You can [make changes to the dependency](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_ModifyProjectTaskDependencies.md) as needed.
- **[Add an external dependency on planning console](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/create-external-dependency-planning-console.md)**
Add an external dependency between two projects on the planning console. Use the work breakdown structure \(WBS\) column of the planning console to create a dependency between the different projects tasks.
- **[Modify a project task dependency](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_ModifyProjectTaskDependencies.md)**
Modify a dependency when editing the tasks that are linked in the dependency, the dependency type, or the lag time.
- **[Remove a dependency](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_RemoveDependencies.md)**
Use the planning console to remove a dependency that is no longer necessary.
**Parent Topic:**[Using Planning console - Legacy](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/c_TheProjectPlanningConsole.md)
**Related topics**
[Open the project planning console]()
[Planning console tasks]()
[Client side planning console]()
[Gantt chart]()
[Create a parent-child relationship on the planning console]()
[Predecessor dependencies in the planning console]()
[Custom columns in the planning console]()
[Modify a project task dependency](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_ModifyProjectTaskDependencies.md)
| title | Create a dependency from the planning console |
| description | Create a dependency between two tasks on the planning console. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/project-management/t\_CreateADependency.html |
| release | brazil |
| product | Project Management |
| classification | project-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 2 |
| breadcrumb | Using Planning console - LegacyUsing Project ManagementProject ManagementProject Portfolio ManagementStrategic Portfolio Management |