Assign a project schedule
Assign a schedule to a project so that task durations and dates reflect real working days and hours.
Before you begin
Role required: it_project_manager
A project uses a schedule to determine which days and hours count as working time. Without an assigned schedule, a project treats every day as a full 24 hours, which makes task durations and the finish date unrealistic. Assign a schedule to base the project on real working time. If the schedules in the base system don't fit your needs, define a new one.
Procedure
-
Open a project.
-
If the Default view is active, right-click the header bar and select View > Advanced.
-
Select a schedule in the Schedule field and select Save.
Parent Topic:Starting a project
Related topics
Create a project task from a project
Create a parent-child relationship on the Project Task form
Create a monetary benefit plan for a project
Create a non-monetary benefit plan for a project
Associate monetary and non-monetary benefit plans
Recalculating costs of all resource plans in a project
Create and manage waterfall projects
Schedule a project from a start date
Apply or change a task constraint
Activate project task email notifications
Change the planned start date of a project
Costing add-on in Project Management
Create a project status report
--- title: Assign a project schedule description: Assign a schedule to a project so that task durations and dates reflect real working days and hours. locale: en-US canonical_url: https://www.servicenow.com/docs/r/it-business-management/project-management/t\_UseAProjectSchedule.html release: brazil product: Project Management classification: project-management topic_type: task last_updated: "2026-09-15" reading_time_minutes: 4 breadcrumb: [Starting a project, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management] --- # Assign a project schedule Assign a schedule to a project so that task durations and dates reflect real working days and hours. ## Before you begin Role required: it\_project\_manager A project uses a schedule to determine which days and hours count as working time. Without an assigned schedule, a project treats every day as a full 24 hours, which makes task durations and the finish date unrealistic. Assign a schedule to base the project on real working time. If the schedules in the base system don't fit your needs, define a new one. ## Procedure 1. Open a project. 2. If the **Default** view is active, right-click the header bar and select **View** > **Advanced**. 3. Select a schedule in the **Schedule** field and select **Save**. **Parent Topic:**[Starting a project](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_CreateAProject.md) **Related topics** [Create a project task from a project]() [Create a parent-child relationship on the Project Task form]() [Create a monetary benefit plan for a project]() [Create a non-monetary benefit plan for a project]() [Associate monetary and non-monetary benefit plans]() [Create a project cost plan]() [Recalculating costs of all resource plans in a project]() [Create an expense line]() [Create and manage waterfall projects]() [Schedule a project from a start date]() [Apply or change a task constraint]() [Update a project]() [Copy a project]() [Create baseline of a project]() [Create a milestone]() [Activate project task email notifications]() [Change the planned start date of a project]() [Create a cost type definition]() [Costing add-on in Project Management]() [Generate labor costs]() [Create a project status report]() [Allocate budget to a project]() [Migrate budget of active projects to Next Experience]() [Migrate financial baselines of projects to Next Experience]()
| title | Assign a project schedule |
| description | Assign a schedule to a project so that task durations and dates reflect real working days and hours. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/project-management/t\_UseAProjectSchedule.html |
| release | brazil |
| product | Project Management |
| classification | project-management |
| topic_type | task |
| last_updated | 2026-09-15 |
| reading_time_minutes | 4 |
| breadcrumb | Starting a projectUsing Project ManagementProject ManagementProject Portfolio ManagementStrategic Portfolio Management |