Task link types
reference brazil Updated Sep 10, 2026 1 min read task-link-types-project-management.md
Task links define the dependency relationship between tasks. Linking tasks creates dependencies that affect task start and finish dates and determine the critical path. The following table describes the four supported link types.
| Link type | Abbreviation | Description |
|---|---|---|
| Finish-to-Start | FS | Task B cannot start until Task A finishes. |
| Start-to-Start | SS | Task B cannot start until Task A starts. |
| Finish-to-Finish | FF | Task B cannot finish until Task A finishes. |
| Start-to-Finish | SF | Task B cannot finish until Task A starts. |
Parent Topic:Project Management reference
Related topics
35 lines · 1.8 KB
--- title: Task link types description: Task links define the dependency relationship between tasks. Linking tasks creates dependencies that affect task start and finish dates and determine the critical path. The following table describes the four supported link types. locale: en-US canonical_url: https://www.servicenow.com/docs/r/it-business-management/project-management/task-link-types-project-management.html release: brazil product: Project Management classification: project-management topic_type: reference last_updated: "2026-09-10" reading_time_minutes: 1 breadcrumb: [Project Management reference, Project Management, Project Portfolio Management, Strategic Portfolio Management] --- # Task link types Task links define the dependency relationship between tasks. Linking tasks creates dependencies that affect task start and finish dates and determine the critical path. The following table describes the four supported link types. |Link type|Abbreviation|Description| |---------|------------|-----------| |Finish-to-Start|FS|Task B cannot start until Task A finishes.| |Start-to-Start|SS|Task B cannot start until Task A starts.| |Finish-to-Finish|FF|Task B cannot finish until Task A finishes.| |Start-to-Finish|SF|Task B cannot finish until Task A starts.| **Parent Topic:**[Project Management reference](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/project-management-reference.md) **Related topics** [Schedule a project from a start date](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/schedule-a-project-pm.md) [Project scheduling in Project Management](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/project-scheduling.md)
| title | Task link types |
| description | Task links define the dependency relationship between tasks. Linking tasks creates dependencies that affect task start and finish dates and determine the critical path. The following table describes the four supported link types. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/project-management/task-link-types-project-management.html |
| release | brazil |
| product | Project Management |
| classification | project-management |
| topic_type | reference |
| last_updated | 2026-09-10 |
| reading_time_minutes | 1 |
| breadcrumb | Project Management referenceProject ManagementProject Portfolio ManagementStrategic Portfolio Management |