Schedule a project from a start date
Schedule a project from a start date and plan tasks and milestones based on your project requirements.
Before you begin
Role required: it_project_manager
Procedure
-
Navigate to All > Project > Projects > Create New.
-
On the Project form, enter the project name.
-
From Dates related list, select Schedule and select Approved start date.
All tasks without dependencies or constraints are set to start on the project start date.
-
Select Submit.
Parent Topic:Starting a project
Related topics
Create a project task from a project
Create a parent-child relationship on the Project Task form
Create a monetary benefit plan for a project
Create a non-monetary benefit plan for a project
Associate monetary and non-monetary benefit plans
Recalculating costs of all resource plans in a project
Create and manage waterfall projects
Apply or change a task constraint
Activate project task email notifications
Change the planned start date of a project
Costing add-on in Project Management
Create a project status report
Migrate budget of active projects to Next Experience
Migrate financial baselines of projects to Next Experience
---
title: Schedule a project from a start date
description: Schedule a project from a start date and plan tasks and milestones based on your project requirements.
locale: en-US
canonical_url: https://www.servicenow.com/docs/r/it-business-management/project-management/schedule-a-project-pm.html
release: brazil
product: Project Management
classification: project-management
topic_type: task
last_updated: "2026-09-10"
reading_time_minutes: 4
breadcrumb: [Starting a project, Using Project Management, Project Management, Project Portfolio Management, Strategic Portfolio Management]
---
# Schedule a project from a start date
Schedule a project from a start date and plan tasks and milestones based on your project requirements.
## Before you begin
Role required: it\_project\_manager
## Procedure
1. Navigate to **All** > **Project** > **Projects** > **Create New**.
2. On the Project form, enter the project name.
3. From Dates related list, select **Schedule** and select **Approved start date**.
All tasks without dependencies or constraints are set to start on the project start date.
4. Select **Submit**.
**Parent Topic:**[Starting a project](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/t_CreateAProject.md)
**Related topics**
[Create a project task from a project]()
[Create a parent-child relationship on the Project Task form]()
[Create a monetary benefit plan for a project]()
[Create a non-monetary benefit plan for a project]()
[Associate monetary and non-monetary benefit plans]()
[Create a project cost plan]()
[Recalculating costs of all resource plans in a project]()
[Create an expense line]()
[Create and manage waterfall projects]()
[Apply or change a task constraint]()
[Update a project]()
[Copy a project]()
[Assign a project schedule]()
[Create baseline of a project]()
[Create a milestone]()
[Activate project task email notifications]()
[Change the planned start date of a project]()
[Create a cost type definition]()
[Costing add-on in Project Management]()
[Generate labor costs]()
[Create a project status report]()
[Allocate budget to a project]()
[Migrate budget of active projects to Next Experience]()
[Migrate financial baselines of projects to Next Experience]()
[Project scheduling in Project Management](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/project-scheduling.md)
[Task link types](https://raw.githubusercontent.com/ServiceNow/ServiceNowDocs/brazil/markdown/it-business-management/project-management/task-link-types-project-management.md)
| title | Schedule a project from a start date |
| description | Schedule a project from a start date and plan tasks and milestones based on your project requirements. |
| locale | en-US |
| canonical_url | https://www.servicenow.com/docs/r/it-business-management/project-management/schedule-a-project-pm.html |
| release | brazil |
| product | Project Management |
| classification | project-management |
| topic_type | task |
| last_updated | 2026-09-10 |
| reading_time_minutes | 4 |
| breadcrumb | Starting a projectUsing Project ManagementProject ManagementProject Portfolio ManagementStrategic Portfolio Management |